Tekar Technical Research Limited
Tekar Technical Research Limited
  • Home
  • COMPANY
    • ABOUT US
    • OUR OFFICES
  • PROJECTS
    • TEKAR IN TURKEY
    • TEKAR IN UZBEKISTAN
    • TEKAR IN TAJIKISTAN
    • TEKAR IN KYRGYZ REPUBLIC
    • TEKAR IN TURKMENISTAN
    • TEKAR IN SAUDI ARABIA
    • TEKAR IN GEORGIA
    • TEKAR IN UGANDA
    • TEKAR IN SIERRA LEONE
    • TEKAR IN COMOROS ISLANDS
  • CONTACT
  • Daha fazlası
    • Home
    • COMPANY
      • ABOUT US
      • OUR OFFICES
    • PROJECTS
      • TEKAR IN TURKEY
      • TEKAR IN UZBEKISTAN
      • TEKAR IN TAJIKISTAN
      • TEKAR IN KYRGYZ REPUBLIC
      • TEKAR IN TURKMENISTAN
      • TEKAR IN SAUDI ARABIA
      • TEKAR IN GEORGIA
      • TEKAR IN UGANDA
      • TEKAR IN SIERRA LEONE
      • TEKAR IN COMOROS ISLANDS
    • CONTACT
  • Home
  • COMPANY
    • ABOUT US
    • OUR OFFICES
  • PROJECTS
    • TEKAR IN TURKEY
    • TEKAR IN UZBEKISTAN
    • TEKAR IN TAJIKISTAN
    • TEKAR IN KYRGYZ REPUBLIC
    • TEKAR IN TURKMENISTAN
    • TEKAR IN SAUDI ARABIA
    • TEKAR IN GEORGIA
    • TEKAR IN UGANDA
    • TEKAR IN SIERRA LEONE
    • TEKAR IN COMOROS ISLANDS
  • CONTACT

TEKAR In Republic of Tajikistan

Project 

Construction of Kulyab – Kalaighkum Road, Shorurabad – Shagon Section (Section B & C)


Client

Republic of Tajikistan, Ministry of Transport


Executed During

2011 – 2017


Main Contractor

COMBINED GROUP – TEKAR J.V.


Project Description

Construction 40.7 km road at rough topography starting over 2,200 m and completion at 1,400 m elevation, including construction of 9 Bridges (with total length over 1 km), slope and flood protection works, drainage structures, Street Lighting, asphalt pavement and other related works. Earth Work (exc) 4,796.820 m3 Earth Work (backfill) 613,643 m3 Concrete works 149,329.34 m3 Asphalt Works 95,420.12 M3 Base Course 485,758 m3


Financed By

ISLAMIC COORDINATION GROUP (Islamic Development Bank, Kuwait Fund, Saudi Fund, Abu Dhabi Fund and OPEC Fund)


Contract Value

92,021,914.59 USD 


Project 

Construction of Shagon – Zigar Road, Lot -1


Client

Republic of Tajikistan, Ministry of Transport


Executed During

2003 - 2006


Main Contractor

COMBINED GROUP – AGE – TEKAR J.V.


Project Description

Construction of 5,8 km of single carriageway road with 9 m platform width at very rough topography, including construction of 1 viaduct and 4 half bridges, slope protection works, drainage structures, and other related works.Excavation of rock with blasting 780,000 m3, Formation of access road 10,000 m3, Excavation of Suitable material 64,000 m3, Structural excavation of rock 13,000 m3, Deposition of rock fill 180,000 m3
Cast in place reinforced concrete 9,660 m3, Pre-splitting holes (50 mm to 125 mm) 75,000 m, Rock bolts and dowels 1,520 m, Shotcrete 7,360 m3


Financed By

Islamic Development Bank


Contract Value

9,388,058.51 USD 

Project 

Dangara Valley Irrigation Project, Lot -1


Client

Republic of Tajikistan, Ministry of Meloeration


Executed During

2002 – 2005


Main Contractor

AGE – TEKAR J.V.


Project Description

Irrigation area is 2,500 hectares. Construction of irrigation channels (lined and earth), prefabricated flumes, surface drainage, sub-surface drainage, irrigation network with PE pipes and hydraulic structures (silt traps, syphones, bridges, pipe crossings, outlets etc). Project also includes treatment of soil subsidence, leand levelling and electric lines. Excavation 5,000,000 m3, Filling 500,000 m3, Cast in place reinforced concrete 21,000 m3, Pre-cast concrete elements k 2,000 m3, Underground drainage pipes 13,000 m, Covered irrigation system PE pipes 75,000 m, Steel pipe works 6,500 m, Irrigation hose pipes 62,500 m, Energy transmission Line 7,000 m


Financed By

Islamic Development Bank


Contract Value

6,549,056.80 USD 

Project 

Excavation of Tailrace Channel of Nurek HPP, Lot-3


Client

Barki Tajik – Republic of Tajikistan


Executed During

2005 – 2008


Main Contractor

TEKAR Ltd.


Project Description

Construction of 2 reinforced concrete dams at Safetob river (Km 0+095 and 0+790), construction of channel at Safetob River (700 m in length), excavation of river bed material at Vakhsh River (668,556.97 m3)


Financed By

ASIAN DEVELOPMENT BANK


Contract Value

4,396,441.34 USD

© TEKAR Teknik Araştırma ve Ticaret Limited Şirketi - Tüm Hakları Saklıdır. 2025.

Bu web sitesinde çerez kullanılır.

Web sitesi trafiğini analiz etmek ve web sitesi deneyiminizi optimize etmek amacıyla çerezler kullanıyoruz. Çerez kullanımımızı kabul ettiğinizde, verileriniz tüm diğer kullanıcı verileriyle birlikte derlenir.

Kabul Et